Skip to content

[request] link with predecessor at specified duration #1776

@garsric

Description

@garsric

Is it possible to add a type of link with predecessor that let the user specify a percentage of the duration of the predecessor as a starting point ? I mean it seems usual to start a task once a certain amount of the predecessor as been achieved and not only whent the full task has been achieved.

Thank's a lot for all the work already done with this software !

Metadata

Metadata

Assignees

No one assigned

    Type

    No type

    Projects

    No projects

    Milestone

    No milestone

    Relationships

    None yet

    Development

    No branches or pull requests

    Issue actions