Smart schedule for many jobs #1225

Closed Answered by vcastellm
pgrandinetti asked this question in Q&A
Discussion options

You must be logged in to vote

Sorry for the late response this slip under my radar.

If there are a thousand jobs all scheduled at 00:00, will Dkron start all of them exactly at that time (regardless of how many nodes there are and what their hardware is)?

It will try to start them almost at the same time yes, depending on resources it can succeed or fail, 1k is not that much it should handle them with decent hardware.

There's no recommendations or benchmarks published, but according to personal experience and benchmarks it can handle tens of thousands of jobs with medium hardware.

Replies: 1 comment

Comment options

You must be logged in to vote
0 replies
Answer selected by pgrandinetti