E49 ("A unit of count defining the number of working days (working day: a day on which work is ordinarily performed)") might be useful e.g. when renting out machines without charging sundays and holidays. If you are talking about person-days AFAIK there is no exact match in the code list. I've seen DAY, E48, LS, H87, C62, XUN,... used with this meaning... |
Beta Was this translation helpful? Give feedback.
-
|
Good morning, Great, thanks. I had something like that in mind too, but one of our customers insisted that E49 was the correct unit for person-days, which made me unsure again... So, with my limited knowledge, it makes sense that "piece" was correct. Thanks, |
Beta Was this translation helpful? Give feedback.
Uh oh!
There was an error while loading. Please reload this page.
-
Hello,
as we started somewhere in the past to create eInvoice we started to use H87 (pieces) for working days after we found a recommendation to do it that way.. Today I have no idea from where we got the information. In the code list I find E49 for Working days, but this is not part of the current implemenation here.
What do you use for working days or can E49 just beadded in the next release?