List view
Q3 2021 milestone.
Due by September 30, 2021•26/26 issues closed- Due by August 18, 2021•2/2 issues closed
- Due by August 4, 2021•2/2 issues closed
- Due by July 21, 2021•15/15 issues closed
Exit criteria: 1. All test cases are either green or have an exception and tracking issue to be addressed in M3: go/kpt-test-cases 2. Reference docs for hydration, packaging and live apply 3. Team wide fishfood for reference docs and Chapter 1 of the book Can get early feedback from users.
Due by May 21, 2021•76/76 issues closedExit criteria: - internal build - all the P1 functionality is working
Due by April 14, 2021•57/57 issues closed- Due by November 25, 2020•5/5 issues closed
- Due by November 11, 2020•8/8 issues closed
- Due by October 28, 2020•3/3 issues closed
Launch kpt: pkg, cfg, fn, docs, blogpost https://github.com/GoogleContainerTools/kpt/issues/420
Due by March 31, 2020•19/19 issues closed