@chair28980 chair28980 commented Oct 6, 2025

Update due dates to 27-Oct for (with justifications):

  • Milestone: Integrate RLN With the Waku API

    • Endianness incompatibilites between nwaku and zerokit
    • Recently bumped zerokit to v0.9.0
    • Perform a refactor in nwaku's RLN code base given that the Merkle tree management is pure onchain
  • Milestone: Improve DevEx: API, TWN, Metrics, Docs

    • Trial quic won't be done in short-term because the nim-libp2p is performing enhancements in there.
    • Big difficulties to properly handle sds+nix+status
    • Invested efforts in evolving nim-ffi + nim-ffi-protobuf for long term benefit across the Logos stack
    • Good progress on Waku API definition and soon we can start implement it in nwaku (createNode done, send WIP)

Copy link
Contributor

@weboko weboko left a comment

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

👍

@fryorcraken
Copy link
Contributor

@Ivansete-status @chair28980 @weboko Thanks for doing that.

Can I have a few bullet points to justify the delays? Also do highlight if a risk previously identified did materialize.

@weboko
Copy link
Contributor

weboko commented Oct 21, 2025

From my side it’s due to re-prioritisation of deliverables rather than delay, even though we had some.

We took other deliverables earlier that this one and thus pushed the deadline.

Also, settling up on common specification was hard to predict and we expected it.

@fryorcraken
Copy link
Contributor

fryorcraken commented Oct 22, 2025

We took other deliverables earlier that this one and thus pushed the deadline.

Which "other deliverables"?

Also, settling up on common specification was hard to predict and we expected it.

What "common specification"?

thx

@Ivansete-status
Copy link
Contributor

Hey there @fryorcraken !
Let me summarize the reasons why those items got delayed:

  • draft-roadmap/improve_devex_api_twn_metrics_docs.md

    • Trial quic won't be done in short-term because the nim-libp2p is performing enhancements in there.
    • Big difficulties to properly handle sds+nix+status
    • Invested efforts in evolving nim-ffi + nim-ffi-protobuf
    • I think there's good progress in the Send API definition and soon we can start implement it in nwaku.
  • draft-roadmap/integrate_rln_with_waku_api.md: we haven't started this deliverable yet. In fact, 27Oct is optimistic.

    • Endianness incompatibilites between nwaku and zerokit
    • Recently bumped zerokit to v0.9.0
    • Add new Global Network Metrics
    • Perform a refactor in nwaku's RLN code base given that the Merkle tree management is pure onchain
    • Prepare release v0.37.0

@fryorcraken
Copy link
Contributor

thanks @Ivansete-status , you say 29Oct is optimistic, let's then review to a realistic date. cc @chair28980
@weboko pleaes provide something similar to @Ivansete-status

Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Labels

None yet

Projects

None yet

Development

Successfully merging this pull request may close these issues.

5 participants